Construction of a section of the S7 Expressway between Kalsk and Miłomłyn
Total quantity of material supplied: 114k tonnes
Construction was undertaken by Strabag. With the TEFRA 15® binder, the contractor was able to achieve the required load-bearing parameters of the improved ground – 40 MPa. TEFRA 25® hydraulic binder was also used to achieve the compressive strength of Rm 1.5 MPa in non-cohesive soils.
Products used: TEFRA 15® and TEFRA 25®
Construction of a section of the S7 Expressway between Ostróda and Olsztynek
Total quantity of material supplied: 68k tonnes
Construction was undertaken by Strabag and Strabag Infrastruktura. By applying the TEFRA 15® and TEFRA 25® binders, the contractor significantly increased the load-bearing parameters, i.e., above 60 MPa. Also, TEFRA 25® was used as an ingredient of the cement-stabilized soil with the capacity of 2.5MPa and 5 MPa. The use of this binder type was intended to improve the grain structure which translated into increased compressive strength.
Products used: TEFRA 15® and TEFRA 25®
Construction of the S2 Expressway: the Warsaw South Ring Road
Total quantity of material supplied: 54k tonnes
Construction was undertaken by Bilfinger Berger Polska. By applying the TEFRA 15® binder, the contractor significantly reduced the level of moisture in cohesive soils.
Products used: TEFRA 15®
Construction of a section of the S3 Expressway between Nowa Sól and Legnica(A4)
Total quantity of material supplied: 40k tonnes
Construction was undertaken by Budimex. By applying the TEFRA 15® binder, the contractor was able to achieve the required load-bearing parameters of embankment layers.
Products used: TEFRA 15®
Construction of the Toruń-Stryków section of the A1 Highway, section III: between Brzezie and Kowal
Total quantity of material supplied: 30k tonnes
Construction of this expressway was undertaken by an Irish construction company SRB. With the TEFRA 15® binder, the contractor was able to achieve the required load-bearing parameters of the improved ground and embankment layers. TEFRA 25® hydraulic binder was also used to achieve the compressive strength of Rm 1.5 MPa in non-cohesive soils.
Products used: TEFRA 15® and TEFRA 25®
Construction of the A4 Highway, section Tarnów – Rzeszów (Tarnów Płn. – Dębica Wsch. ), (Dębica Wsch. – Rzeszów Zach.)
Total quantity of material supplied: 81,36 tonnes
Construction of the S5 Expressway, section Gniezno – Czachurki
Total quantity of material supplied: 571,78 tonnes
Construction of the S5 Expressway, section Nowe Marzy – Dworzysko
Total quantity of material supplied: tonnes
Construction of the S5 Expressway, section Dworzysko – Aleksandrowo
Total quantity of material supplied: 22 588,28 tonnes
Construction of the S5 Expressway, section Aleksandrowo – Tryszczyn
Total quantity of material supplied: tonnes
Construction of the S5 Expressway, section Białe Błota – Szubin
Total quantity of material supplied: tonnes
Construction of the S5 Expressway, section Szubin – Jaroszewo
Total quantity of material supplied: tonnes
Construction of the S5 Expressway, section Leszno – Kaczkowo
Total quantity of material supplied: 1 057,60 tonnes
Construction of the S5 Expressway, section Kaczkowo – Kościan
Total quantity of material supplied: tonnes
Construction of the S6 Expressway, section Sianów – Koszalin
Total quantity of material supplied: 1 438,64 tonnes
Construction of the S6 Expressway, section Koszalin – Kołobrzeg
Total quantity of material supplied: tonnes
Construction of the S6 Expressway, section Kołobrzeg Zachód – Ustronie Morskie
Total quantity of material supplied: 55 594,84 tonnes
Construction of the S6 Expressway, section Goleniów – Nowogard
Total quantity of material supplied: 5 020,32 tonnes
Construction of the S7 Expressway, section Ostróda Beltway
Total quantity of material supplied: 10 768,48 tonnes
Construction of the S8 Expressway, section Salomea – Wolica (urban section)
Total quantity of material supplied: 2 071,56 tonnes
Construction of the S8 Expressway, section Jeżewo – Białystok
Total quantity of material supplied: 3 203,60 tonnes
Construction of the S8 Expressway, section Salomea – Wolica (non-urban section Opacz – Paszków)
Total quantity of material supplied: tonnes
Construction of the S8 Expressway, section Węzeł Syców Zachodni
Total quantity of material supplied: 27,52 tonnes
Construction of the S8 Expressway, section Sieradz – Złoczew
Total quantity of material supplied: 1 212,36 tonnes
Construction of the S8 Expressway, section Kobyłka – Radzymin
Total quantity of material supplied: tonnes
Construction of the S8 Expressway, section Kobyłka – Marki
Total quantity of material supplied: tonnes
Construction of the S17 Expressway, section Kurów – Lublin – Piaski
Total quantity of material supplied: tonnes
Construction of the S17 Ryki Expressway
Total quantity of material supplied: 1 041,72 tonnes
Construction of the Access Road to Lublin City Beltway – extension of the Mełgiewska Street
Total quantity of material supplied: tonnes
Construction of the Access Road to the Dąbrowic Junction (section from the crossroads Al.Solidarności with Al. Warszawska to the city limits) in Lublin
Total quantity of material supplied: tonnes
Construction of the Ciechanów City Beltway
Total quantity of material supplied: 2 000,22 tonnes
Construction of the Mogilno City Beltway
Total quantity of material supplied: tonnes
Construction of the Mielec City Beltway
Total quantity of material supplied: tonnes
Construction of the Płock City Beltway
Total quantity of material supplied: 1 663,42 tonnes
Construction of the Wałcz City Beltway
Total quantity of material supplied: 4 921,60 tonnes
Construction of the Augustów City Beltway
Total quantity of material supplied: 10 223,19 tonnes
Construction of the Leżajsk City Beltway
Total quantity of material supplied: 54,46 tonnes
Construction of the Nowogard City Beltway
Total quantity of material supplied: tonnes
Construction of the Słupsk City Beltway
Total quantity of material supplied: 643,74 tonnes
Construction of the Western Beltway of Poznań
Total quantity of material supplied: 5 241,32 tonnes
Construction of the Zambrów City Beltway
Total quantity of material supplied: 16 593,71 tonnes
Reconstruction of the DK 65, section Gołdap – Kowale Oleckie
Total quantity of material supplied: 1 182,54 tonnes
Reconstruction of the DW 515, section Lidzbark Warmiński – Orneta
Total quantity of material supplied: 28,16 tonnes
Construction of the S6 Expressway, section Płoty – Kiełpino
Total quantity of material supplied: tonnes
Reconstruction of the DK 11, section Złotkowo – Bogdanowo
Total quantity of material supplied: 109,96 tonnes
Reconstruction of the DW 196, section Murowana Goślina – Wągrowiec
Total quantity of material supplied: 110,16 tonnes
Reconstruction of the DW 768, section Koszyce – Brzesko
Total quantity of material supplied: 450,92 tonnes
Reconstruction of the Nowolazurowa Street in Warsaw
Total quantity of material supplied: tonnes